Tuesday, September 29, 2009

More progress at the new location...

Things are moving right along... the sprinkler system is up and operational, concrete's been poured, and the electricians and plumbers are working on the taproom area. We bought a good used cooler at an auction today (RIP Rosario's, sorry to see you go), that will go behind the bar to hold kegs for serving the taproom. This week we will knock out an opening in the back wall of the brewery to get ready for the new brewhouse, which will arrive next week! If you happen to drive by the new location on next Tues or Wed, you may see a crane and several trucks, delivering our new 40 bbl brewhouse! Just don't try to talk to me, because I will be sweating bullets and biting fingernails, hoping we get them unloaded and inside the building with no problems. It's going to take two cranes and a lot of rigging, but it's not going to be as hard as getting tanks into our Marathon location has been!

1 comment:

Anonymous said...

got pics of the new location??